Fort Mill's Exit 85 Interchange Is Running Late: What's Built, What's Left, and What Comes Next on I-77

"There should've been a utility window in the contract before we awarded it to the contractor, and it didn't get added in until later. So we needed more time to get those utilities moved out."

That is how Josh Meetze, a program manager with the South Carolina Department of Transportation, explained to the Rock Hill Herald why the Interstate 77 and S.C. 160 interchange in Fort Mill will open later than planned. The project was scheduled to open in November 2027. The estimate is now May 30, 2028, about six months later. According to the Herald, the extension adds time but no cost.

Six months is a small slip for a project whose first funding was approved in 2015. The bigger news for Fort Mill drivers is south of the state line. Once Exit 85 is done, the next upgrade on the I-77 corridor in Fort Mill is Exit 90 at Carowinds Boulevard, and that work is waiting on decisions made in Charlotte.

What six extra months buys on S.C. 160

The utility relocation sets the new date, but crews are already well along. As of the Herald's October 1 update:

  • Both ramp bridges are complete.
  • All of the project's walls are complete.
  • The first part of the S.C. 160 bridge over the interstate is finished, and girders are being set.
  • Widening on the south side of S.C. 160 is underway.
  • Work on the interstate median is underway.

At $165 million, this is York County's most expensive interstate upgrade to date. Most of the money, $99.3 million, comes from the Rock Hill-Fort Mill Area Transportation Study. The South Carolina Transportation Infrastructure Bank put in $42.2 million, and York County put in $23.4 million. The project got state infrastructure bank funding in 2021, construction bids were approved two years later, and officials broke ground on March 11, 2024.

What drivers between Baxter and Kingsley get in 2028

SCDOT calls the design a South Carolina first. It is built to cut down left-turn conflicts on S.C. 160, space the intersections better, and reduce congestion. The work also widens more than a mile of S.C. 160 between U.S. 21 and Pleasant Road. According to the Herald, the finished interchange is fully directional. It has one signalized intersection and three new bridges, and two of those bridges are interstate flyovers. A 10-foot-wide multi-use path runs along the widened road.

All of that has to work on a busy road. SCDOT traffic counts put S.C. 160 at nearly 23,000 vehicle trips per day in this area, according to a June 2026 Herald report. That same report shows how closures here have been routed. In June 2026, SCDOT scheduled the S.C. 160 intersections at Market Street and Munn Road to close for about a week. The Herald described Market Street as the main entrance to Baxter's commercial area of restaurants and shops. It described Munn Road as near several large employers, Kingsley, and Fort Mill High School.

The detours used for those closures still show the way around each of these points:

Closed point on S.C. 160 Area it serves Detour SCDOT used
Market Street Main entrance to Baxter's shops and restaurants Assembly Drive
Munn Road Kingsley, nearby employers, Fort Mill High School U.S. 21 and Harris Road, about half a mile

In April 2026, crews also closed eastbound and westbound S.C. 160 lanes at the interchange overnight, from 7 p.m. to 6 a.m., April 8 through 12. Through traffic on I-77 was not expected to be affected.

More of this is coming before May 2028. Drivers may start using parts of the new interchange before the final completion date, and more traffic shifts are expected in the last months. Jason Johnston, an engineering administrator at SCDOT, told the Herald, "Traffic will end up going in a final pattern, then there'll be individual lane closures as they put the final lift of asphalt on it." SCDOT's project site for the S.C. 160 interchange has a downloadable exhibit of the final design and is the place to check before a trip across the bridge.

Exit 85 sits in the middle of a county-long rebuild

Exit 85 is one project in a series of interchange upgrades that York County has been working through on I-77, one exit at a time:

Exit Location Status, per the Herald's October 2026 report
88 Gold Hill Road, Fort Mill South Carolina's first diverging diamond interchange, opened about five years ago for $14.5 million
81 Rock Hill Opened about two years ago, a $90 million new interchange
85 S.C. 160, Fort Mill Under construction, now estimated for May 30, 2028
82 Cherry and Celanese roads, Rock Hill $106 million, with construction expected to begin in 2030
90 Carowinds Boulevard, Fort Mill Received $2 million in state money for a study of upgrade options

Rock Hill's Exit 82 already has a construction year. Fort Mill's other major interchange, Exit 90 at Carowinds, has only a study, and it sits on the North Carolina line.

Why the next move at Carowinds depends on Charlotte

In November 2025, SCDOT announced that it would coordinate with NCDOT at the state border and take over management of Exit 90 improvements from York County. That project phase was estimated at $3 million and covered preliminary engineering, right-of-way and construction activities. The $2 million feasibility study was first announced in December 2024. It was to focus on cars and freight, and the layout and timing were still undecided.

That study cannot move far by itself. In May 2026, RFATS administrator David Hooper told the Herald that the Carowinds interchange feasibility study needed clarity on North Carolina's I-77 plans before taking its next step. The Herald's October report also says transportation officials are discussing how the Carowinds interchange might work if North Carolina extends toll lanes from Charlotte to the South Carolina line.

North Carolina took a step in September. On Monday, September 21, Charlotte City Council voted 7-4 to restore its support for the I-77 South express lanes, WFAE reported. Two days later, the Charlotte Regional Transportation Planning Organization reinstated its resolution asking NCDOT to "move forward with a public-private partnership delivery process," and only Matthews and Mecklenburg County voted no, according to WSOC.

NCDOT's project page, last updated October 16, 2026, describes the plan:

  • Limits: about 11 miles, from the South Carolina state line to I-277/N.C. 16, the Brookshire Freeway
  • Scope: express lanes, rebuilt interchanges and bridges, and new access points and direct connectors
  • Estimated cost: $3.2 billion
  • Status: "In Development," with start and completion dates listed as TBD
  • Funding: preliminary engineering is the only phase funded in the current state transportation improvement program
  • Public meetings: none scheduled

WFAE reported that the next steps after the September vote are environmental analysis, community meetings and proposals from developers before any construction. The lanes are projected to open "next decade."

What this means for Fort Mill drivers

Fort Mill now has a finish date for one interchange and an open question at the other. Exit 85 has its walls and ramp bridges in place and a May 30, 2028 target. Exit 90 depends on a North Carolina toll-lane project that cleared a key vote this fall but has no construction schedule. For the next year and a half, S.C. 160 between Baxter and Kingsley is where construction will affect daily trips. Assembly Drive and the U.S. 21 to Harris Road route are the detours SCDOT has already used here, and SCDOT's S.C. 160 project site and press releases are where new closures are posted.